The Nepal Electricity Authority (NEA) has received approval to import 350 megawatts (MW) of electricity from India during the current winter season.
The Central Electricity Authority under India's Ministry of Power has granted permission to the NEA to import electricity at competitive rates from the Day-Ahead and Real-Time markets of the Indian Energy Exchange (IEX) for up to 17 hours daily.
The NEA can import electricity from November 17, 2026 to July 31, 2027.
Under the approval, electricity can be imported from the IEX at any time except from 5:00 am to 8:00 am and 5:00 pm to 9:00 pm, according to NEA.
As per the approval, 300 MW of electricity can be imported through the Kataiya-Kushaha, Ramnagar-Surajpura and Raxaul-Parwanipur 132 kV transmission lines, while the remaining 50 MW can be imported through the New Nautanwa-Mainahiya 132 kV transmission line.
Managing Director of NEA Dirghayu Kumar Shrestha said that the approval to import 350 MW of electricity from India would make it easier to manage electricity demand and supply during the upcoming winter season.
He said that necessary preparations had been made to manage electricity demand and supply during the winter, taking into account the damage caused to hydropower projects and transmission lines by the glacial flood that entered the Trishuli River through the Bhotekoshi River in Rasuwa.
As a result, hydropower projects with a combined installed capacity of 431 MW have been disconnected from the national grid.
According to an analysis based on last year's electricity demand and generation patterns, domestic demand is expected to exceed internal production for four months—from mid-December to mid-April. During this period, Nepal will need to import electricity from India.
In particular, the country is expected to require an average continuous import of 450 to 500 MW of electricity daily during mid-January to mid-March.
Similarly, during peak demand hours, electricity imports could reach 800 to 900 MW per day. Imports are expected to be relatively lower in Poush and Chait.
From Baisakh (mid-April) onwards, water levels in rivers are expected to gradually rise, increasing domestic electricity generation. This is expected to reduce dependence on imports and pave the way for electricity exports.
Approval to export 56 MW of Electricity
The NEA has also received approval to sell a total of 56 MW of electricity generated by three hydropower projects in the Indian Energy Exchange (IEX).
The authority can export the electricity from November 17, 2026 to July 31, 2027.